Delivery record
Built across substations, solar and transmission.
Every project here ran from first-issue drawings to energization sign-off under one contract. Capacity, voltage class and timeline are on record.
Selected projects
Three sectors. Documented scope.

Substation EPC
132 kV grid substation
Full EPC delivery: civil, structural, primary equipment and protection systems.
- Voltage
- 132 kV
- Capacity
- 2 × 40 MVA
- Delivery
- Energized on schedule at 18 months

Solar EPC
50 MW solar generation plant
Design, procurement and construction of a ground-mounted array with its collector substation.
- Capacity
- 50 MW DC
- Collector
- 33 kV substation
- Delivery
- Grid-connected and commissioned at 22 months

Transmission line
220 kV double-circuit line
Tower design, foundations, stringing and protection relay commissioning.
- Voltage
- 220 kV double circuit
- Length
- 85 km overhead line
- Delivery
- Full handover at 14 months