Delivery record

Built across substations, solar and transmission.

Every project here ran from first-issue drawings to energization sign-off under one contract. Capacity, voltage class and timeline are on record.

Selected projects

Three sectors. Documented scope.

Power transformer in a 132 kV substation
Substation EPC

132 kV grid substation

Full EPC delivery: civil, structural, primary equipment and protection systems.

Voltage
132 kV
Capacity
2 × 40 MVA
Delivery
Energized on schedule at 18 months
Ground-mounted solar array
Solar EPC

50 MW solar generation plant

Design, procurement and construction of a ground-mounted array with its collector substation.

Capacity
50 MW DC
Collector
33 kV substation
Delivery
Grid-connected and commissioned at 22 months
Crane erecting a 220 kV transmission tower
Transmission line

220 kV double-circuit line

Tower design, foundations, stringing and protection relay commissioning.

Voltage
220 kV double circuit
Length
85 km overhead line
Delivery
Full handover at 14 months

Ready to scope your project?

Bring us your voltage class, site constraints and timeline. We will tell you exactly what full-cycle delivery looks like for your project.